Data investigation · SEAP procurement records and the trade register

Your road comes with a warranty. Is the firm that paved it still standing?

A road paid for with public money comes with a warranty, and the warranty starts with the firm that built it. Type your town or village and see who paved its roads since July 2023, and what the trade register says about those firms today.

Of 712 road contracts signed in the second half of 2023, on 33 a builder has entered insolvency, bankruptcy or dissolution since signing. In all, since 1 July 2023: 78 of 2,901 contracts (2.7%). The data does not show road firms entering insolvency more often than other firms; the issue is that a road warranty lasts years, and public data does not show the warranty itself: its length, its form, and whether anyone ever called it.

Every contract, in one chart

78 contracts where a builder entered insolvency, bankruptcy or dissolution after signing

Each dot is a contract. Horizontal: when it was signed. Vertical: the month an insolvency, bankruptcy or dissolution entry appeared in the trade register for one of its builders. A filled dot above the dashed line means the entry came after signing. Contracts of the same firm sit on the same horizontal row.

entry appeared after signingfirm already had the entrydate unclearall 2,901 contracts, per month
Dot size follows the published estimated value; a small translucent dot means no value is published. Entries are dated with 24 trade-register extracts, July 2023 to November 2026: the vertical position is the first extract in which the entry shows. Yellow dots below the line (7) are contracts signed with a firm that already had the entry. The hollow circles (3) are contracts where the date cannot be fixed: the entry is in the register but was not caught between two extracts without it. Click a dot to open its town.
78contracts out of 2,901 with a builder that entered insolvency, bankruptcy or dissolution after signing
20have a single builder; on the other 58, other members remain in the contract
1.5bn leipublished estimated value; 35 contracts have no published value

By signing year

Signing yearContractsWith a builder in insolvency, bankruptcy or dissolution after signing%
2023712334.6%
2024872323.7%
2025862121.4%
202645510.2%

Older contracts have had more time: that is why the share falls towards 2026. The shares exclude the unclear ones.

On the 78 contracts, 38 firms received the entry after signing (insolvency: 33, bankruptcy: 3, dissolution: 2). Five firms hold 29 of the contracts and one alone holds 9: the cases are concentrated in a few firms.

How often a builder enters insolvency

The data does not show road firms entering insolvency more often than others

Of the firms that were active and had no such entry on 6 October 2025, the share that had an insolvency, bankruptcy or dissolution entry on 19 October 2026 (378 days later) was:

All active firms in Romania · 1,735,793 firms2.12% (2.10%–2.14%)
Firms with at least 10 employees · 51,414 firms1.49% (1.39%–1.60%)
Civil engineering (roads, railways, other works), at least 10 employees · 687 firms2.33% (1.44%–3.75%)
Builders in the road contracts on this page · 1,201 firms1.58% (1.02%–2.46%)
The same, with at least 10 employees · 756 firms1.19% (0.63%–2.25%)

Black line: 95% confidence interval. Firm = unique registration code. Employee counts are from the 2025 balance sheets, filed after the start of the window: firms that disappeared in between are missing from the size groups.

The confidence intervals overlap, so the data does not show road firms entering insolvency more often than others. If the 1.6% over a little more than a year kept up, a firm would have roughly 8 chances in 100 of receiving such an entry within five years. The five-year figure is a rough extrapolation, not an observation.

The conclusion is not that road firms are suspect. It is that a road warranty lasts years and an ordinary firm may be gone in that time. What stands behind the warranty then matters: a bank’s letter, an insurance policy, or only the firm.

Where the cases are

59 towns and villages, plus 15 contracts of other authorities

The table follows the same contracts as the chart. Click a place to see its contracts and builders.

AuthorityCountyContractsPublished estimated valueEntry appeared

at least one contract with a builder that entered insolvency, bankruptcy or dissolution after signingcontracts with unclear datecontracts without cases · grey: no contract in SEAP
1,546 of 3,187 administrative units have at least one road-works contract published in SEAP since July 2023. Outlines: geo-spatial.org, CC BY-SA 4.0.

What the data cannot show

What the data says and does not say

  • “Warranty” means two different things: the warranty period on the works (how long the builder answers for defects) and the performance guarantee (the money or letter that backs it). The data shows neither.
  • SEAP does not publish the works’ handover, the warranty length, or whether anyone called the guarantee. The page shows only who signed and what the trade register says about the firms in the contract.
  • A firm’s insolvency does not by itself cancel the guarantee: it depends on its form (a bank letter, an insurance policy or a retained sum). The form of each contract’s guarantee is not in the data.
  • An insolvency entry does not say the road was badly built. It says only what the register records about the firm.
  • On 1,173 of 2,901 contracts the builder is several firms (a consortium or separate lots). A contract is counted if any member received the entry; who answers for the warranty inside a consortium depends on the consortium agreement.
  • Missing values: in the public file, 489 of 872 contracts from 2024 and 189 of 712 from 2023 have no published value; from 2025 on, all do. Sums on this page are published estimates, not payments.
  • Criminal-liability entries: for 41 of the firms in these contracts the register shows a criminal-liability or referral-to-trial entry, in 283 contracts. The register does not say what offence, so the page gives only the count.
  • Contracts signed before 1 July 2023 are not counted: 751 appear in the file with earlier dates.

Ask for the proof

What you can ask your town hall

  1. The handover (reception) minutes at completion of the works: when were they signed and what defects or remarks do they list?
  2. How long is the warranty on the works and until when does it run?
  3. In what form is the performance guarantee (bank letter, insurance policy, retained sum) and who holds it?
  4. Were defects reported after reception? If so, what did the town hall ask of the builder, and when?
  5. If a builder entered insolvency: did the town hall file a claim in the insolvency or call the guarantee?

Pick your place at the top: the request is filled in automatically with the contract numbers of that place. Law 544/2001 (Romania’s freedom-of-information law) requires a reply within 10 days, or at most 30 for complex requests, with notice to you within the first 10. The request is in Romanian, because the authority will read it.

Pick your place

Facebook X Email

Method

How contracts and entries are counted

SourcePeriodRole
SEAP/SICAP via data.gov.ro, CPV 452331* rows (road and street works)July 2023 – October 20262,901 contracts signed from 1 July 2023 to 29 September 2026, summed estimated value 102.1bn lei.
Trade register (ONRC), 24 public extracts of firm states, data.gov.roJuly 2023 – November 2026The states in force for each firm on the extract date: dissolution, liquidation, bankruptcy, judicial reorganisation, insolvency. The extracts are compared with each other.
ONRC, firm list and state nomenclature6 October 2025 and 19 October 2026Link between tax code and registration numbers; the meaning of each code.
Ministry of Finance, 2025 balance sheets2025Employee counts, to compare with firms of similar size.
Tax code → SIRUTA (ANAF) and LAU outlines2025–2026Link between contracting authority and locality; the map.

Rules

  1. A contract here is one SEAP award notice (CAN or SCNA number); one notice can hold several contracts, for example lots with different winners. Its date is the earliest date among its rows; its value is the maximum of its rows, because SEAP repeats the contract value for every member of an association. A zero or missing value means “not published”.
  2. Builders are identified by tax code. A firm can change its registration number (for example when moving its registered office to another county); the old number then shows as “struck off”. All numbers a firm carried in the October 2025 and October 2026 files are therefore pooled, and a strike-off is not counted as an entry.
  3. Entries counted: dissolution, liquidation, bankruptcy, judicial reorganisation and insolvency (codes 1049, 1052, 1070, 1057, 1107, 1139, 1083, 1073 and related; the nomenclature words code 1139 as “is under Law 85/2014”). Criminal liability (2127, 1036) is counted separately and attributed to no firm.
  4. “After signing”: the firm was seen active and without the entry in the extract before the one in which the entry appears, and that extract is dated on or after the signing day. If the firm was missing from the earlier extract, the date is “unclear”, not “clean”. The entry is placed at the date of the first extract in which it appears; the real date falls between that extract and the one before. A state seen in two consecutive extracts is assumed to have been in force between them; a few firms have entries that disappear and return, so the assumption is not certain.
  5. Base rate: firms active and without an entry on 6 October 2025, by tax code, that have an entry on 19 October 2026. The confidence interval is Wilson, 95%. Extracts before May 2025 are quarterly and in another layout, with the tax code on each row; states are read the same way. In all, 1,221 of 1,250 firms appear in the extracts before May 2025, and 27 appear in none (foreign firms or firms struck off long ago).
Correction, 14 November 2026. The first version of this page counted 419 contracts (23.38 billion lei) with undated register entries, in contracts signed between 2016 and 2026, and it counted strike-offs too. It has been replaced: entries are now dated with the monthly register extracts, only contracts from 1 July 2023 are counted, and strike-offs and criminal liability no longer enter the case count. The section on maintenance within two years of modernisation was removed: matching was by authority, not by road, and for 16 of the 38 pairs the modernisation contract had no published value.

Data and code

The analysis can be redone from the files above and the public register extracts. Data: SEAP/SICAP and ONRC via data.gov.ro (OGL-ROU-1.0), Ministry of Finance, ANAF, INS (SIRUTA), geo-spatial.org (CC BY-SA 4.0). Reuse: “Marius Comper, mariuscomper.uk/asfaltul-care-se-rupe-in-garantie”.