MHCLG / England / 26 August 2026

data to 31 July

Nearly three quarters of the buildings where work has not started are recorded with no remediation plan

In the Ministry of Housing, Communities and Local Government's latest table, 974 of 1,357 buildings are in the category "not started, no plans in place". That is 71.8%, rounded to 72%.

One division brings the number inside the total into view.

Segmented bar for 2,621 buildings: 596 complete or awaiting sign-off, 668 with work started, 383 not started with a plan in place, and 974 not started with no plan in place. The last category represents 72% of buildings where work has not started.
Main chart All 2,621 buildings in one 4:5 bar. Red marks the category examined here, not a verdict on any individual building.
Download the 4:5 chart

The numbers behind the calculation

2,621

buildings with life-critical fire-safety defects

1,357

buildings where remediation has not started

974

recorded with no remediation plan

72%

of buildings where work has not started

The number inside the total

37% of the whole becomes 72% when the denominator matches the question

MHCLG identifies 2,621 buildings with life-critical fire-safety defects under the developer remediation contract. Developers have committed to remediate the defects or pay for remediation, including cases where work is carried out through a government-funded programme.

Viewed as a whole, the table says that 37% of the buildings are in the category "not started, no plans in place". That is the number you get when you divide 974 by all 2,621 buildings. The more useful question is what is happening inside the group where work has not started.

That group contains 383 buildings with a plan in place and 974 buildings recorded with no remediation plan. Divide 974 by 1,357 and 71.8% of the group still at the starting line falls into the second category.

MHCLG also estimates 168,000 dwellings in all buildings with defects. Of those, 89,000 are in buildings where work has started or completed. The difference is about 79,000 dwellings in buildings where remediation has not started. The public totals cannot split that number between the two plan-status categories.

See the calculation step by step
2,621total1,264started or completed=1,357not started
974no plan recorded÷1,357not started=71.8%

The visual shows 71.8% as 72% for a quick read. The calculation uses the whole-number values published by MHCLG.

The source table

How the 2,621 buildings are divided

Remediation status in MHCLG's July 2026 table
Reported statusBuildingsOf total
Complete or awaiting building-control sign-off59623%
Work started66825%
Not started, plan in place38315%
Not started, no plan in place97437%
Total2,621100%

The limit that matters

"No plan in place" is a reporting category

The label does not prove that no conversation, draft or preparatory action has existed. It describes how a case appears in MHCLG's table. The page keeps that wording next to the percentage so 72% is not read as an inspection of every building.

How to read the series

The inputs have different reference dates

The edition published on 26 August 2026 reports the position at 31 July 2026. For the buildings in the contract, developer data is as at 30 April 2026 and is received quarterly. MHCLG also updates the series with monthly information from other remediation programmes and imputes some fields when information is missing.

The approximately 79,000 dwellings cover all buildings where work has not started. The source does not show how many sit in each plan-status category.

Primary sources

Read the table in its own context