BRĂILA · LOWER DANUBE
Grain in336 cells
At Brăila’s docks, grain first went up to the roof. From there it dropped into the silo, then travelled under the quay to the ship.
Follow the grainIn the silo annex
Buckets lift the grain
Grain could arrive in a railway wagon or by water. In the annex it passed through cleaning machines and scales. Buckets fixed to an endless belt took it up to the gallery.
A belt in the upper gallery carried it to the selected cell. The grain then fell through the inlet.
Inside the silo
Choose a cell
Anghel Saligny built adjoining cells from reinforced concrete panels. A study of the structure counts 185 cells of 100 t and 151 of 50 t.
Viewed from above, the six-sided cells share walls. In the model, you can see how much grain goes into each cell and how much space is left.
Below the dock
Under the quay and aboard
Open the outlet of a filled cell. Grain runs down a chute onto a lengthwise belt. Other belts carry it across the quay and then along the waterfront.
In 1898, the journal Prometheus described 15 masonry wells by the water. Elevators took the grain from the wells to the ship’s loading hatch.
Inside the wall
Iron inside concrete
The reinforced panels were made at ground level. Iron loops stuck out from their edges. During assembly, a vertical rod passed through adjacent loops and the joint was filled with mortar.
The structural study gives a wall thickness of 16 cm in the lower zone and 12 cm higher up. It records panels, joints and departures from the specified thickness in the cells surveyed.