The Prut · Stânca–Costești

Two waves, one river

The design-flood chart for Stânca–Costești combines two waves resembling events in 1972 and 1985. The first peak comes on day 12; the second on day 46.

Scroll to follow the story

Two peaks

The water arrives in two waves

The technical design for Stânca–Costești follows a 75-day flood. A synthesis published by Romania’s water administration describes two waves resembling floods in 1972 and 1985.

The first peak is 2,800 m³/s on day 12. The second is 1,850 m³/s on day 46. Thirty-four days separate them.

One shared basin

One river, three countries

Stânca–Costești is on the middle Prut, at the border between Romania and the Republic of Moldova. Its contributing catchment covers about 12,000 km² across Romania, Moldova and Ukraine.

The 3D landscape here is an illustrative model made to follow the water. It is not a topographic survey and does not draw the border.

The 1971 agreement

The agreement set out shared uses

Romania and the Soviet Union signed the agreement for the hydrotechnical complex in 1971. It provided for equal shares of regulated water volume and generated electricity.

The agreement set out cooperation between the states before construction began. Institutions on both banks have continued to administer the Prut works jointly.

Several dates

Acceptance and inauguration took place on different dates

Work began in 1973. Romania's water administration records provisional acceptance and temporary operation on 29 June 1978. The contractor dates the inauguration to 4 November 1978 and says the works were accepted in 1979.

The intergovernmental commission signed final acceptance on 13 December 1984. Each date marks a different step in the same project.

The water balance

Where does the model's water go?

Move the cursor through the 75 days. The input curve marks two peaks with the published values. Its shape between them is schematic because the source gives peak rates and their timing, not a full daily series.

Below, a teaching model divides 100 normalized units between water already out and water held temporarily: cumulative input = cumulative output + water remaining in storage. The curve and release rule in this exercise do not describe operation of the hydrotechnical complex.

Follow the day on the chart

The source gives the timing and discharge of the two peaks. The line between them is schematic.

Inflow · published peaksm³/s
A schematic 75-day hydrograph with the published peaks on days 12 and 46, and a balance of normalized water units. 2 8002 0001 0000 012344675 Day in the design flood
Inflow · published peaks• The two peak discharges and their days come from the hydrotechnical synthesis. The line between peaks is a curve drawn here as a schematic.

The model balance accounts for the same amount of water at every step.

100 units
The model balance accounts for the same amount of water at every step. 100500
Entered the model
0
Left the model
0
Still stored
0
How the model works

The model normalizes input across the 75 daily intervals from day 0 to day 75, to a total of 100 units. For each interval, input is the mean of the curve values at its endpoints. Then 8% of the storage remaining at that step becomes output. The equation is cumulative input = cumulative output + storage remaining. These values are not measured discharges and do not describe operation of the hydrotechnical complex.

What it is for

One reservoir, several purposes

The 1971 agreement lists different uses: regulating river flow for irrigation and water supply, reducing flood effects downstream, generating electricity and supporting navigation within the agreed limits.

The reservoir serves needs on both banks: irrigation, water supply, reducing flood effects downstream, electricity and navigation. The catchment that feeds it reaches far beyond the dam.

Share the chart

Two peaks, 34 days apart, in one design flood.

Back to projects

Sources and dates

The two peak discharges and their days come from the hydrotechnical synthesis. The line between peaks is a curve drawn here as a schematic.

  1. Romanian Waters, Hidrotehnica 2024, pp. 20–30

    Catchment, agreement, joint administration, design flood and 1978–1984 milestones.

  2. Hidroconstructia, “Stânca–Costești Hydrotechnical System on the Prut (II)”

    The contractor's technical history, including the start of work and its inauguration date.

  3. Costești Hydropower Plant, profile

    Plant location and context of the Prut basin.