United Kingdom · public network · 1 July 2026
How can the same network have 97,266 devices and 121,171 EV chargers?
Because the unit changes. The Department for Transport counts physical boxes separately from EVSE that each control one charging session.
Official DfT source · estimated coverage above 95% · official statistics in development
Numerical difference: 23,905. These are not 23,905 extra boxes.
01 / The same infrastructure
Four correct answers to “how many?”
Change only the unit being counted. The schematic stays fixed: one invented location, two devices, three EVSE and five connectors.
Location
A geographic place containing one or more charging devices.
Device
The physical charging unit. One box can contain more than one EVSE.
EVSE
The unit that controls one charging session at a time. DfT calls it an “EV charger”.
Connector
The physical plug. One EVSE can have several plugs, but they do not necessarily support simultaneous sessions.
02 / Choosing the unit
EVSE better approximates separately controlled sessions
Devices can undercount potential availability. Connectors can overcount it.
But EVSE is not a promise
An EVSE does not guarantee that a driver can charge immediately. Outages, occupied bays, power limits and hardware design can reduce simultaneous use.
Changing the unit also changes how the network can be compared over time.
03 / The series break
The baseline changed in 2026
The historic device series continues, and the EVSE series has quarterly points from January 2025. Compare values within the same series; do not join unlike units into one line.
04 / A fall that removed no hardware
An operator corrected access, not physical chargers
In the June 2026 feed, about 1,270 private-access EVSE had been reported incorrectly as public. Removing them from the public dataset lowered the total, but it did not describe physical disappearance.
05 / Reading the next total
Four questions before you compare
- 01
Which unit? Location, device, EVSE or connector.
- 02
Which date? A statistical snapshot is not a live counter.
- 03
Which access? Public, private or a mixture.
- 04
The same series? Do not splice devices and EVSE into one trend.
Method and limits
A measurement lesson, not a network ranking
The totals are DfT's snapshot for UK public infrastructure on 1 July 2026. They are not live figures. DfT estimates that its sources cover above 95% of the network and may revise the series.
The schematic with totals of 1, 2, 3 and 5 is invented to illustrate the definitions. The national gap of 23,905 is not a count of extra boxes, installed power or guaranteed sessions.
Decisive sources
- DfT: statistics at 1 July 2026
- DfT: definitions and frequently asked questions
- DfT: EVCI data tables
Published 27 August 2026 · Data accessed 27 August 2026 · Markdown edition