Heat substation 1 Colentina: days without hot water, 2022–2026
Sector 2
Of these: 0 from modernisation works, 14 from breakdowns, 2 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · maintenance or other
16 August 2026 – 17 August 2026
Oprire CTE Grozăvești în vederea înlocuirii racord apă, Apa Nova
Latest works shutdown
16 September 2025 – 19 September 2025
Modernizare retea primara PMB-SAEM
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 24 | 9 | 33 |
| 2023 | 1 | 52 | 10 | 63 |
| 2024 | 38 | 17 | 8 | 63 |
| 2025 | 13 | 15 | 2 | 30 |
| 2026 | 0 | 14 | 2 | 16 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Mașina de Pâine – bl.2, T111, 1
- Str Vaporul lui Assan – bl.4
- Str Irimicului – bl.1, 2, 3