Heat substation 1 Drumul Sarii: days without hot water, 2022–2026
Sector 5
Of these: 27 from modernisation works, 9 from breakdowns, 4 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest works shutdown
13 October 2026 – 16 October 2026
Lucrări de reabilitare a sistemului de termoficare al Municipiului Bucuresti executate de către Asocierea Energomontaj SA (lider) - SC Elsaco Electronic SRL - SC Sicor SRL și IPCT Instalatii SRL
firm named in the notice: Elsaco
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 2 | 69 | 8 | 79 |
| 2023 | 0 | 33 | 2 | 35 |
| 2024 | 1 | 35 | 0 | 36 |
| 2025 | 30 | 14 | 4 | 48 |
| 2026 | 27 | 9 | 4 | 40 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Ale Botorani – bl. V44, V50, V57, V49, V51
- Cal 13 Septembrie – bl. V53, V54, V47, V46, V45
- Drm Sării – bl. V58, V60, V55
- Str Năbucului – bl. V59