Heat substation 1 Laborator: days without hot water, 2022–2026
Sector 3
39days without hot water · In 2026, to 23 October
Of these: 32 from modernisation works, 5 from breakdowns, 2 from maintenance and other causes.
2026, day by day
JanFebMarAprMayJunJulAugSepOct
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest works shutdown
20 July 2026 – 5 August 2026
Execuție lucrări de modernizare - firma ELSACO pe Magistrala II Sud
firm named in the notice: Elsaco
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 21 | 5 | 26 |
| 2023 | 12 | 29 | 18 | 59 |
| 2024 | 22 | 21 | 1 | 44 |
| 2025 | 9 | 24 | 2 | 35 |
| 2026 | 32 | 5 | 2 | 39 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Șos Mihai Bravu – bl. V10, V18, V7, V11, V12, V9, V15, V16, V8, V13, V17
- Str Laborator – bl. V14
- Str Iancu Brezeanu – bl. V31B
- Str Agatha Bârsescu – bl. V26C, V31A, V30B, V26A, V28, V30A, V26B, V29, V25, V27A, V27B
- Str Alexander Von Humboldt – bl. V23A
- Ale Blăjel – bl. V5, V6
- Str Breaza – bl. V24A, V23B
- Str Aniversării – bl. 39A