Heat substation 1 Republicii: days without hot water, 2022–2026
Sector 2
Of these: 14 from modernisation works, 6 from breakdowns, 0 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
8 September 2026 – 8 September 2026
Remediere avarie rețea secundară pe circuitul de apă caldă de consum bl.D3
Latest works shutdown
12 May 2026 – 22 May 2026
Lucrari de modernizare SACET
firm named in the notice: Compania Municipală Energetica București
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 2 | 29 | 8 | 39 |
| 2023 | 4 | 24 | 10 | 38 |
| 2024 | 37 | 36 | 0 | 73 |
| 2025 | 12 | 11 | 1 | 24 |
| 2026 | 14 | 6 | 0 | 20 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.