Heat substation 13 Foișor: days without hot water, 2022–2026
Sector 3
Of these: 20 from modernisation works, 20 from breakdowns, 1 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
22 September 2026 – 25 September 2026
Depistat si remediat avarie retea primara
Latest works shutdown
20 July 2026 – 2 August 2026
Execuție lucrări de modernizare - firma ELSACO pe Magistrala II Sud
firm named in the notice: Elsaco
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 39 | 2 | 41 |
| 2023 | 0 | 23 | 8 | 31 |
| 2024 | 0 | 9 | 3 | 12 |
| 2025 | 2 | 26 | 2 | 30 |
| 2026 | 20 | 20 | 1 | 41 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Vlaicu Vodă – bl. V62, V63, V61
- Str Brândușelor – bl.V64
- Str Foișorului – bl. F6C, F7C, F5C, F4C
- Str Alexandru Moruzzi Voievod – bl. V60, V59, V58