Heat substation 16 C5/2: days without hot water, 2022–2026
Sector 3
Of these: 3 from modernisation works, 18 from breakdowns, 0 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
17 August 2026 – 20 August 2026
Avarie retea primara Dn 800 b-dul 1 Decembrie 1918
Latest works shutdown
11 August 2026 – 13 August 2026
Lucrari de modernizare SACET-Obiectiv3 si Reabilitarea sistemului de termoficare al Municipiului Bucuresti-Obiectiv 1 Magistrala I Sud
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 41 | 3 | 44 |
| 2023 | 0 | 23 | 18 | 41 |
| 2024 | 0 | 24 | 5 | 29 |
| 2025 | 2 | 31 | 5 | 38 |
| 2026 | 3 | 18 | 0 | 21 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Ale Perișoru – bl. H34, H35, H36
- Ale Giurgeni – bl.F6, F7, F8, F9, F10, F11, F12, F13, F14
- Str Gura Ialomiței – bl. PC8, PC9, PC10, PC11,H33,H32 PC12, H28, H29, H30, H31
- Str Fetești – bl. V13, H27
- Ale Perișoru -
- Ale Giurgeni -
- Str Fetești -
- Str Pătulului -
- Ale Fetești – bl. F6, V13, H27