Heat substation 18 Pantelimon: days without hot water, 2022–2026
Sector 2
Of these: 0 from modernisation works, 47 from breakdowns, 5 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · maintenance or other
2 October 2026 – 2 October 2026
Lipsa parametri pentru livrare apă caldă de consum
Latest works shutdown
26 March 2024 – 29 March 2024
Lucrari de modernizare POIM-Magistrala 1 Sud,LOT 1 Obiectiv 3
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 29 | 6 | 35 |
| 2023 | 7 | 28 | 21 | 56 |
| 2024 | 4 | 52 | 8 | 64 |
| 2025 | 0 | 39 | 6 | 45 |
| 2026 | 0 | 47 | 5 | 52 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Fântânica – bl.204, 203, imob.Nr.14A
- Șos Pantelimon – bl.206, 205sc.A,B, 400B, 400A, 400C
- Ale Cislău – bl.10, 9A