Heat substation 2 Bucurestii Noi: days without hot water, 2022–2026
Sector 1
Of these: 0 from modernisation works, 7 from breakdowns, 0 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
8 April 2026 – 8 April 2026
Remediere avarie rețea secundară pe circuitul de apă caldă de consum
Latest works shutdown
5 July 2024 – 6 July 2024
Lucrări de reparatii si modernizare a conducelor de retea primara executate de CMTEB si Compania Energetica
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 18 | 1 | 19 |
| 2023 | 0 | 19 | 4 | 23 |
| 2024 | 2 | 39 | 3 | 44 |
| 2025 | 0 | 21 | 3 | 24 |
| 2026 | 0 | 7 | 0 | 7 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Surorilor – bl. A2
- Str Subcetate – bl. A10
- Str Străbună – bl. A1
- Str Șaradei – bl. A9 ,imobil nr.80
- Str Lăstărișului – bl. B2
- Str Crinului – bl. A3, A4, A5
- Str Bârlogeni – imobil Nr.38
- Bld Bucureștii Noi – bl. B1, B3
- Str Pieții – bl. A8, A6, A7
- Str Munteniei -