Heat substation 2 Cornul Caprei: days without hot water, 2022–2026
Sector 3
35days without hot water · In 2026, to 23 October
Of these: 19 from modernisation works, 15 from breakdowns, 1 from maintenance and other causes.
2026, day by day
JanFebMarAprMayJunJulAugSepOct
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
20 October 2026 – 21 October 2026
Avarie racord primar PT.
Latest works shutdown
13 October 2026 – 14 October 2026
Izolare RT CS 4 DECEBAL - CL 2/ FL 4 - 9 MB, pentru executie lucrari firma.
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 14 | 4 | 18 |
| 2023 | 0 | 17 | 12 | 29 |
| 2024 | 0 | 14 | 2 | 16 |
| 2025 | 0 | 25 | 1 | 26 |
| 2026 | 19 | 15 | 1 | 35 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Școala Ciocanu – Imobil
- Bld Burebista – D13, D14