Heat substation 2 Stefan cel Mare: days without hot water, 2022–2026
Sector 2
Of these: 28 from modernisation works, 18 from breakdowns, 2 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
14 October 2026 – 17 October 2026
Izolare Tronson CS6-CS12 pentru depistare și remediere avarii.
Latest works shutdown
13 July 2026 – 1 August 2026
Lucrari de modernizare conducta Dn-600 retea termica primara, magistrala II-III Grozavesti,obiectiv 4,executate de ENERGETICA
firm named in the notice: Energetica
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 28 | 10 | 38 |
| 2023 | 0 | 50 | 6 | 56 |
| 2024 | 6 | 36 | 7 | 49 |
| 2025 | 9 | 11 | 2 | 22 |
| 2026 | 28 | 18 | 2 | 48 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Șos Ștefan cel Mare – bl18,18A,18b,19,22,23,20,15A,14,Imob.nrbv 20
- Str Polonă – bl 17A+B,15
- Str Paul Greceanu – bl 24A, 21A, 21, 20A
- Str Aurel Vlaicu – bl 19A,20,Imob nr 166
- Str Aurel Vlaicu -