Heat substation 2 Virtuții: days without hot water, 2022–2026
Sector 6
Of these: 0 from modernisation works, 19 from breakdowns, 4 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
21 September 2026 – 21 September 2026
Remediere avarie rețea secundară pe circuitul de apă caldă de consum (str.Veteranilor.)
Latest works shutdown
7 December 2023 – 7 December 2023
Lucrări de întregire a rețelei Magistrala III VEST și integrare a conductelor nou înlocuite DN 800
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 26 | 6 | 32 |
| 2023 | 1 | 40 | 4 | 45 |
| 2024 | 0 | 14 | 3 | 17 |
| 2025 | 0 | 22 | 3 | 25 |
| 2026 | 0 | 19 | 4 | 23 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Dreptății – bl. A6, A3B
- Șos Virtuții – bl. R4A
- Str Veteranilor – bl. B3, B4, B6, B8
- Bld Uverturii – bl. B1, B2, A2
- Str Dealul Țugulea – bl. A4, A5, B5B, B5C, B9
- Cal Apeductului – bl. A1, A3A, B5A, B7, B4 A+B, A4B, A4A
- Int Apeductului – bl. A1, A3A, B5A, B7, B4 A+B, A4B, A4A