Heat substation 24 C5/2: days without hot water, 2022–2026
Sector 3
Of these: 3 from modernisation works, 17 from breakdowns, 1 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
17 August 2026 – 20 August 2026
Avarie retea primara Dn 800 b-dul 1 Decembrie 1918
Latest works shutdown
11 August 2026 – 13 August 2026
Lucrari de modernizare SACET-Obiectiv3 si Reabilitarea sistemului de termoficare al Municipiului Bucuresti-Obiectiv 1 Magistrala I Sud
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 51 | 0 | 51 |
| 2023 | 0 | 27 | 20 | 47 |
| 2024 | 0 | 63 | 8 | 71 |
| 2025 | 0 | 52 | 2 | 54 |
| 2026 | 3 | 17 | 1 | 21 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.