Heat substation 3/10: days without hot water, 2022–2026
Sector 6
Of these: 0 from modernisation works, 14 from breakdowns, 4 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
17 August 2026 – 17 August 2026
Remediere avarie racord primar
Latest works shutdown
8 April 2025 – 9 April 2025
Inlocuit conducta DN 400,zona B-dul 1 Mai.Lucrari de intregire a conductei intre caminele CC2 si CC3 si dotare a caminului CC2.
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 24 | 0 | 24 |
| 2023 | 4 | 23 | 1 | 28 |
| 2024 | 0 | 24 | 2 | 26 |
| 2025 | 2 | 14 | 1 | 17 |
| 2026 | 0 | 14 | 4 | 18 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Vlădeasa – bl. C67, C77, C68, C74 SCARA B, C75, C39, C34, C48
- Str Serg. Gheorghe Lățea – bl. C70, C71, C47, C36, C60, C37, C35, C61, C69, C74-SCARA A
- Bld Ghencea – bl.C66, C65, C64, C63, C24, C25, C26
- Str Gârleni – bl. C45, C46, C72, C73
- Str Constantin Titel Petrescu – bl. C23, C62, C38, C40