Heat substation 4 Cheile Zanoagei: days without hot water, 2022–2026
Sector 2
Of these: 16 from modernisation works, 24 from breakdowns, 2 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
14 October 2026 – 14 October 2026
Remediere avarie rețea secundară pe circuitul de apă caldă de consum
Latest works shutdown
25 May 2026 – 28 May 2026
Lucrari de modernizare-firma ELSACO
firm named in the notice: Elsaco
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 30 | 8 | 38 |
| 2023 | 5 | 16 | 25 | 46 |
| 2024 | 2 | 23 | 4 | 29 |
| 2025 | 41 | 45 | 1 | 87 |
| 2026 | 16 | 24 | 2 | 42 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Alexandru cel Bun – BL.T61; T50 sc.1
- Str Deleni – bl.T69, T65, T63; T66, T74, T64
- Str Grigore Ionescu – bl.T71, T75, T72, T59, T60, T73
- Str Maica Domnului – bl.T56, T57, T58, T54, T55, T52, T53, T51, T50 sc.2
- Str Oteșani – bl.T70, T68, T67, T62
- Str Alexandru cel Bun -
- Str Deleni -
- Str Grigore Ionescu -
- Str Oteșani -
- Str Sfîntul Vasile Tei – bl.T74, T66, T64