Heat substation 5 Crivina: days without hot water, 2022–2026
Sector 6
26days without hot water · In 2026, to 23 October
Of these: 5 from modernisation works, 15 from breakdowns, 6 from maintenance and other causes.
2026, day by day
JanFebMarAprMayJunJulAugSepOct
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
30 September 2026 – 3 October 2026
Depistare și remediere avarie racord primar
Latest works shutdown
31 March 2026 – 4 April 2026
LUCRARI MODERNIZARE-POIM-LOT 2-OBIECTIV 11
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 21 | 3 | 24 |
| 2023 | 0 | 30 | 3 | 33 |
| 2024 | 7 | 61 | 0 | 68 |
| 2025 | 8 | 28 | 5 | 41 |
| 2026 | 5 | 15 | 6 | 26 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Olănești – bl. 38, 43
- Str Fraților – bl. 85
- Str Vintilă Mihăilescu – bl. 42A
- Str Zboina Neagră – bl. 88
- Str Porumbacu – bl. 33, 30, 35, 34, 87, 86, 31
- Str 9 Mai – bl. 24, 36, 37, 25, 25bis
- Str Ceahlăul – bl. 28, 29, 32, 38A, 39,27, 26 sc. 1
- Cal Crângași – bl. 42, 26 sc. 2+3, 40, 41, 84, 43A