Heat substation 6 Aviatiei: days without hot water, 2022–2026
Sector 1
Of these: 33 from modernisation works, 19 from breakdowns, 3 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
14 October 2026 – 17 October 2026
Remediere avarie circuit primar -
Latest works shutdown
13 July 2026 – 1 August 2026
Lucrari de modernizare conducta Dn-600 retea termica primara, magistrala II-III Grozavesti,obiectiv 4,executate de ENERGETICA
firm named in the notice: Energetica
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 4 | 83 | 4 | 91 |
| 2023 | 0 | 91 | 7 | 98 |
| 2024 | 3 | 61 | 1 | 65 |
| 2025 | 13 | 24 | 3 | 40 |
| 2026 | 33 | 19 | 3 | 55 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Nicolae G. Caramfil – bl. 21H, 21B, 21A, 21C, 22 B
- Str G-ral Ștefan Burileanu – bl. 20A, 20C, 20B, 21E
- Str Cpt. Alexandru Șerbănescu – bl. 20-I, 20J, 22H, 20E, 20D
- Str Smaranda Brăescu – bl. 20H, 20F, 21 I, 21G, 22D, 21F
- Str Zăgazului – bl. 20F, 21F
- Str Liliacului – bl. 20A, 20B
- Str Bujorului – bl. 20I
- Str Herăstrău – bl. 21A, 21B, 21C, 21H, 22B