mariuscomper.uk RO

← All heat substations

Heat substation 7 Doamna Ghica: days without hot water, 2022–2026

Sector 2

8days without hot water · In 2026, to 23 October

Of these: 0 from modernisation works, 8 from breakdowns, 0 from maintenance and other causes.

2026, day by day

worksbreakdownsmaintenance and otherweak hot waterno shutdown announced

Each square is a day. Coloured means the substation appears shut that day, even for a few hours.

Days without hot water, year by year

Latest shutdown · breakdown

31 August 2026 – 1 September 2026

Remediere avarie racord primar

Latest works shutdown

13 October 2025 – 18 October 2025

Rețea Primară Tronson CP3-CG9-CC13, Fundeni,str.D-na Ghica,str.Vulcanei,str.Baicului. Rețea Primară Tronson CG9-CO2 Colentina,str.D-na Ghica,Ion Berindei.Se vor executa lucrări de montare vane -SACET-LOT2 și LOT 4.Anul de punere în funcțiun

See it on the map

YearWorksBreakdownsMaintenance and otherTotal
2022059867
2023582134
2024228636
20254433178
20260808

2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.

Blocks supplied