Heat substation 7 Margeanului: days without hot water, 2022–2026
Sector 5
Of these: 33 from modernisation works, 26 from breakdowns, 3 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
22 October 2026 – 22 October 2026
Remediere avarie rețea secundară pe circuitul de apă caldă de consum (str.Cap. Ivan Anghelache)
Latest works shutdown
7 October 2026 – 9 October 2026
Lucrari de reabilitarea sistemului de termoficare al Municipiului Bucuresti, Lot 5 - Obiectiv 14
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 4 | 28 | 11 | 43 |
| 2023 | 3 | 17 | 3 | 23 |
| 2024 | 2 | 33 | 4 | 39 |
| 2025 | 13 | 38 | 1 | 52 |
| 2026 | 33 | 26 | 3 | 62 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Cap. Ivan Anghelache – bl. M29, M30, M31, M32, M33, M34
- Str Sold. Ene Modoran – bl. M93A, M93B
- Str Dumbrava Nouă – bl. M78 scara 1, M79
- Str Buzoeni – bl. M38, M39, M40, M41, M76, M77, M78 scara 2
- Str Mărgeanului – bl. M35, M36, M37