Heat substation 7X: days without hot water, 2022–2026
Sector 3
Of these: 4 from modernisation works, 16 from breakdowns, 0 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
19 October 2026 – ongoing
Remediere avarie retea primara - str. Baba Novac /str. Câmpia Libertăţii :
Latest works shutdown
14 August 2026 – 17 August 2026
Lucrari de modernizare SACET-Obiectiv3 si Reabilitarea sistemului de termoficare al Municipiului Bucuresti-Obiectiv 1 Magistrala I Sud
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 24 | 3 | 27 |
| 2023 | 0 | 27 | 17 | 44 |
| 2024 | 0 | 23 | 3 | 26 |
| 2025 | 5 | 38 | 1 | 44 |
| 2026 | 4 | 16 | 0 | 20 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Liviu Rebreanu – bl.49, 50, 50A
- Str Câmpia Libertății – bl.34A, 35A
- Int Reconstrucției – bl.28bis, 29