Heat substation Beller Bitolia: days without hot water, 2022–2026
Sector 1
Of these: 33 from modernisation works, 16 from breakdowns, 2 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
14 October 2026 – 16 October 2026
Remediere avarie circuit primar -
Latest works shutdown
13 July 2026 – 1 August 2026
Lucrari de modernizare conducta Dn-600 retea termica primara, magistrala II-III Grozavesti,obiectiv 4,executate de ENERGETICA
firm named in the notice: Energetica
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 4 | 30 | 2 | 36 |
| 2023 | 13 | 61 | 7 | 81 |
| 2024 | 3 | 42 | 0 | 45 |
| 2025 | 13 | 14 | 1 | 28 |
| 2026 | 33 | 16 | 2 | 51 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str N. Constantinescu – bl. 9, 11, 11A
- Str Lt. D. Darian – bl. 11B, 23
- Str Lt. Radu Beller – bl. 20, 22
- Str Gen. Andrei Popovici – bl. 6, 1+1B
- Str Ștefan Protopopescu – bl. 24
- Str Puțul lui Zamfir – bl. 20A