Heat substation Dealul Cernei: days without hot water, 2022–2026
Sector 4
55days without hot water · In 2026, to 23 October
Of these: 50 from modernisation works, 5 from breakdowns, 0 from maintenance and other causes.
2026, day by day
JanFebMarAprMayJunJulAugSepOct
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest works shutdown
28 September 2026 – 13 October 2026
Reabilitarea sistemului de termoficare ,lucrari POIM ,Lot 4, Obiective 17,19,21
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 17 | 1 | 18 |
| 2023 | 0 | 18 | 5 | 23 |
| 2024 | 0 | 7 | 0 | 7 |
| 2025 | 10 | 15 | 0 | 25 |
| 2026 | 50 | 5 | 0 | 55 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Uioara – bl. 12Bis, 35, 36, 46
- Ale Cetatea Veche – bl. 2Bis, 3Bis, 5, 37, 38, 39, 40, 41, 47