Heat substation E2 Vatra Luminoasa: days without hot water, 2022–2026
Sector 2
40days without hot water · In 2026, to 23 October
Of these: 0 from modernisation works, 39 from breakdowns, 1 from maintenance and other causes.
2026, day by day
JanFebMarAprMayJunJulAugSepOct
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
3 September 2026 – 5 September 2026
Remediere avarie circuit primar
Latest works shutdown
26 March 2024 – 29 March 2024
Lucrari de modernizare POIM-Magistrala 1 Sud,LOT 1 Obiectiv 3
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 27 | 6 | 33 |
| 2023 | 7 | 18 | 17 | 42 |
| 2024 | 4 | 38 | 2 | 44 |
| 2025 | 0 | 15 | 2 | 17 |
| 2026 | 0 | 39 | 1 | 40 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Vatra Luminoasă – bl. 1
- Str Lt. Victor Manu – bl. C1, C2, E1
- Str Ciurea – bl. Y2, A1, A2, A3, Y1, E2