Heat substation Institutul Boli Infectioase Matei Bals: days without hot water, 2022–2026
Sector 2
Of these: 0 from modernisation works, 3 from breakdowns, 0 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
17 April 2026 – 19 April 2026
Izolare tronson CS11-CS6-C02 Stefan-Colentina-CG9-CFT3-17/18 Petricani, pentru depistare si remediere avarii.
Latest works shutdown
26 August 2024 – 31 August 2024
Lucrari de modernizare din cadrul proiectului "Reabilitarea retelei primare de termoficare" aferenta Magistrala II SUD-LOT 5-Obiectiv 5
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 6 | 0 | 6 |
| 2023 | 0 | 24 | 5 | 29 |
| 2024 | 16 | 21 | 1 | 38 |
| 2025 | 0 | 0 | 0 | 0 |
| 2026 | 0 | 3 | 0 | 3 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.