Heat substation M107: days without hot water, 2022–2026
Sector 3
Of these: 20 from modernisation works, 20 from breakdowns, 2 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
4 September 2026 – 4 September 2026
Remediere avarie rețea secundară pe circuitul de apă caldă de consum,bl. M106
Latest works shutdown
20 July 2026 – 2 August 2026
Execuție lucrări de modernizare - firma ELSACO pe Magistrala II Sud
firm named in the notice: Elsaco
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 36 | 2 | 38 |
| 2023 | 0 | 10 | 6 | 16 |
| 2024 | 0 | 21 | 3 | 24 |
| 2025 | 0 | 23 | 3 | 26 |
| 2026 | 20 | 20 | 2 | 42 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Bld Octavian Goga – bl. M106
- Str Nerva Traian – bl. K6
- Str Emil Botta – bl. M109, M105, M104, M107, M108
- Bld Unirii – bl. K3, K4, K2, K5
- Str Lucian Blaga – bl. K1