Heat substation Oanta Petre: days without hot water, 2022–2026

Sector 3

0days without hot water · In 2026, to 23 October

Of these: 0 from modernisation works, 0 from breakdowns, 0 from maintenance and other causes.

2026, day by day

worksbreakdownsmaintenance and otherweak hot waterno shutdown announced

Each square is a day. Coloured means the substation appears shut that day, even for a few hours.

Days without hot water, year by year

Latest shutdown · breakdown

5 December 2022 – 6 December 2022

Remediere avarii conducta tur DN1000 CET Sud - F8 - CI2.

See it on the map

YearWorksBreakdownsMaintenance and otherTotal
2022011011
20230000
20240000
20250000
20260000

2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.

Blocks supplied