mariuscomper.uk RO

← All heat substations

Heat substation P.D.: days without hot water, 2022–2026

Sector 3

21days without hot water · In 2026, to 23 October

Of these: 0 from modernisation works, 21 from breakdowns, 0 from maintenance and other causes.

2026, day by day

worksbreakdownsmaintenance and otherweak hot waterno shutdown announced

Each square is a day. Coloured means the substation appears shut that day, even for a few hours.

Days without hot water, year by year

Latest shutdown · breakdown

18 August 2026 – 22 August 2026

Depistare si remediere avarii retea primara Mag. III.

Latest works shutdown

29 October 2025 – 31 October 2025

Izolare tronson C RELEULUI -F8,deblindare retea de termificare DN 1000 (tur-retur).

See it on the map

YearWorksBreakdownsMaintenance and otherTotal
20220808
20230121224
20240909
2025315018
2026021021

2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.

Blocks supplied