Heat substation REGIE 3: days without hot water, 2022–2026
Sector 6
39days without hot water · In 2026, to 23 October
Of these: 9 from modernisation works, 28 from breakdowns, 2 from maintenance and other causes.
2026, day by day
JanFebMarAprMayJunJulAugSepOct
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
16 October 2026 – 16 October 2026
Remediere avarie retea primara
Latest works shutdown
10 September 2026 – 11 September 2026
Reabilitarea sistemului de termoficare, Lot 2, Obiectiv 7
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 15 | 0 | 15 |
| 2023 | 0 | 63 | 4 | 67 |
| 2024 | 0 | 57 | 0 | 57 |
| 2025 | 6 | 39 | 5 | 50 |
| 2026 | 9 | 28 | 2 | 39 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Spl Independenței – CAMIN P7, P8, P9, P10, P11, P12, P13, P14, CANTINA VEST, CANTINA EST