Heat substation ROMEXPO S.A. Pavilion A9-A10: days without hot water, 2022–2026
Sector 1
1days without hot water · In 2026, to 23 October
Of these: 0 from modernisation works, 1 from breakdowns, 0 from maintenance and other causes.
2026, day by day
JanFebMarAprMayJunJulAugSepOct
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
25 February 2026 – 25 February 2026
Lucrari de blindare tronson retea primara executate de echipele SLR si remediere punctuala a avariilor retea primara executate de echipele SRP GROZAVESTI
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 0 | 0 | 0 |
| 2023 | 0 | 0 | 0 | 0 |
| 2024 | 0 | 4 | 0 | 4 |
| 2025 | 0 | 2 | 1 | 3 |
| 2026 | 0 | 1 | 0 | 1 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Bld Mărăști -