Heat substation SC 11: days without hot water, 2022–2026
Sector 6
Of these: 0 from modernisation works, 8 from breakdowns, 0 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
7 August 2026 – 7 August 2026
Remediere avarie rețea secundară pe circuitul de apă caldă de consum
Latest works shutdown
14 July 2025 – 17 July 2025
Lucrări de remediere pe rețeaua primară specifice perioadei de garanție în proiectul POIM-cond.DN 400
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 28 | 0 | 28 |
| 2023 | 28 | 21 | 1 | 50 |
| 2024 | 4 | 17 | 5 | 26 |
| 2025 | 4 | 21 | 1 | 26 |
| 2026 | 0 | 8 | 0 | 8 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Str Partiturii – bl. 66
- Str Floare Roșie – bl. 65
- Str Estacadei – bl. 81, 82, N14
- Str Ghirlandei – bl. 64, 78, 79, 80