Heat substation SC.6C3/2 - Module Termice: days without hot water, 2022–2026
Sector 3
Of these: 9 from modernisation works, 10 from breakdowns, 7 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
20 August 2026 – 21 August 2026
Remediere avarie racord primar - Str Liviu Rebreanu
Latest works shutdown
11 August 2026 – 20 August 2026
Lucrari de modernizare SACET-Obiectiv3 si Reabilitarea sistemului de termoficare al Municipiului Bucuresti-Obiectiv 1 Magistrala I Sud
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 20 | 9 | 29 |
| 2023 | 0 | 32 | 14 | 46 |
| 2024 | 0 | 19 | 5 | 24 |
| 2025 | 0 | 21 | 7 | 28 |
| 2026 | 9 | 10 | 7 | 26 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Ale Solidarității – Modul bl.M36A
- Str Liviu Rebreanu – Module bl.M13, M14, M15, M16, M24, M36
- Ale Barajul Bistriței – Module bl. G2, G3, G4