Heat substation SC Conexir Roell Group SA: days without hot water, 2022–2026
Sector 4
Of these: 0 from modernisation works, 3 from breakdowns, 0 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · breakdown
23 February 2026 – 25 February 2026
Remediere avarie circuit primar - Piata Revolutiei x Calea Serban Voda
Latest works shutdown
17 July 2023 – 21 July 2023
Remediere avarie CI10-CMO3 (Sos. Oltenitei nr. 35-37) ;Reintregire tronson CB4-CB2 (Bld.Brancoveanu nr. 20)
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 4 | 0 | 4 |
| 2023 | 5 | 3 | 0 | 8 |
| 2024 | 0 | 24 | 0 | 24 |
| 2025 | 0 | 3 | 0 | 3 |
| 2026 | 0 | 3 | 0 | 3 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Șos Olteniței -