Heat substation Spital Municipal: days without hot water, 2022–2026
Sector 5
Of these: 0 from modernisation works, 7 from breakdowns, 1 from maintenance and other causes.
2026, day by day
worksbreakdownsmaintenance and otherweak hot waterno shutdown announced
Each square is a day. Coloured means the substation appears shut that day, even for a few hours.
Days without hot water, year by year
Latest shutdown · maintenance or other
27 July 2026 – 27 July 2026
Lucrare tehnica programata in cadrul CTE Grozavesti, necesara pentru functionarea in conditii de siguranta a instalatiilor de gaz natural ( efectuarea releveului diafragmei de gaz in vederea inlocuirii acesteia )
| Year | Works | Breakdowns | Maintenance and other | Total |
|---|---|---|---|---|
| 2022 | 0 | 1 | 0 | 1 |
| 2023 | 0 | 3 | 0 | 3 |
| 2024 | 0 | 25 | 0 | 25 |
| 2025 | 0 | 19 | 3 | 22 |
| 2026 | 0 | 7 | 1 | 8 |
2026 stops on 23 October. A day without hot water is a calendar day on which the substation appears shut, even for a few hours, for all its blocks or only some. Each day is counted once, by the cause announced most often that day.
Blocks supplied
- Spl Independenței – Nr. 169 - institutie