mariuscomper.uk RO

The cold in the contract

Heat substation 1/7': hours of below-standard hot water, 2025–2026

Sector 6

190Reconstructed hours with a notice of hot water below standard · in 2025

250 national threshold: 250 hours per year and contract · local threshold: total waiver

Calendar dates with at least one captured notice: 22

The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.

YearHot water below standard, hoursDates with a noticeHeating below standard, hoursHot water off, hoursHeating off, hours
20251902218533174
2026*743045017

* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.

Last captured notice (original, in Romanian) · 2026-10-13 10:55

Remediere avarie rețea secundară pe circuitul de apă caldă de consum (str.Dr. Taberei.)

• Str Drumul Taberei - bl OD1,OD2,TD18 • Ale Vlăsiei - bl. M1, M2, M3 • Str Râul Doamnei - bl.TD5, TS4, TS3, TS2, TS1 • Str Valea lui Mihai - bl TD7, TD6

Streets named in the notices

Outages and their causes, on this substation’s page in “Why your hot water is off”

The cold in the contract →