Heat substation 1 Mosilor: hours of below-standard hot water, 2025–2026
Sector 2
250 national threshold: 250 hours per year and contract · local threshold: total waiver
Calendar dates with at least one captured notice: 38
The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.
| Year | Hot water below standard, hours | Dates with a notice | Heating below standard, hours | Hot water off, hours | Heating off, hours |
|---|---|---|---|---|---|
| 2025 | 317 | 38 | 198 | 841 | 268 |
| 2026* | 300 | 40 | 180 | 464 | 100 |
* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.
Last captured notice (original, in Romanian) · 2026-10-08 19:57
Remediere avarie rețea secundară pe circuitul de apă caldă de consum
• Ale Cenuşeresei - bl.50, 52 • Str Traian - bl.30 B, imob.Nr.254 • Cal Moşilor - bl.36, 38, 42, 46, 48, 58, 32, 30A, 31A , 31C • Str Mihai Eminescu - bl.31B ,32 • Str Vaselor - bl.34, imob.Nr.3A • Str Ion Maiorescu - bl.44 ;50 ;40, imob.Nr.37, 7
Streets named in the notices
- Ale Cenuşeresei
- Str Traian
- Cal Moşilor
- Str Mihai Eminescu
- Str Vaselor
- Str Ion Maiorescu
Outages and their causes, on this substation’s page in “Why your hot water is off”