Heat substation 2/7' - Partial: hours of below-standard hot water, 2025–2026
Sector 6
357Reconstructed hours with a notice of hot water below standard · in 2025
250 national threshold: 250 hours per year and contract · local threshold: total waiver
Calendar dates with at least one captured notice: 45
The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.
| Year | Hot water below standard, hours | Dates with a notice | Heating below standard, hours | Hot water off, hours | Heating off, hours |
|---|---|---|---|---|---|
| 2025 | 357 | 45 | 189 | 83 | 0 |
| 2026* | 17 | 5 | 3 | 71 | 0 |
* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.
Last captured notice (original, in Romanian) · 2026-10-15 12:24
Înlocuire conducta în punctul termic pe circuitul de apă caldă de consum
• Ale Valea Călugărească - Bl. A10,
Streets named in the notices
- Str Braşov
- Str Valea Călugărească
- Prl Ghencea
- Str Chilia Veche
- Str Valea lui Mihai
- Str Valea Roşie
- Ale Valea Roşie
- Ale Valea Călugărească - A10
- Ale Valea Călugărească
Outages and their causes, on this substation’s page in “Why your hot water is off”