Heat substation 3 Labirint: hours of below-standard hot water, 2025–2026
Sector 3
250 national threshold: 250 hours per year and contract · local threshold: total waiver
Calendar dates with at least one captured notice: 19
The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.
| Year | Hot water below standard, hours | Dates with a notice | Heating below standard, hours | Hot water off, hours | Heating off, hours |
|---|---|---|---|---|---|
| 2025 | 209 | 19 | 90 | 413 | 81 |
| 2026* | 570 | 65 | 233 | 626 | 157 |
* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.
Last captured notice (original, in Romanian) · 2026-10-15 12:24
Izolare RT CS 4 DECEBAL - CL 2/ FL 4 - 9 MB, pentru executie lucrari firma.
• Str Matei Basarab - bl. 119bis, L121, L118A, L116A • Str Labirint - bl. L117, L119, L117bis
Streets named in the notices
- Str Matei Basarab
- Str Labirint
Outages and their causes, on this substation’s page in “Why your hot water is off”