mariuscomper.uk RO

The cold in the contract

Heat substation 3 Uverturii: hours of below-standard hot water, 2025–2026

Sector 6

190Reconstructed hours with a notice of hot water below standard · in 2025

250 national threshold: 250 hours per year and contract · local threshold: total waiver

Calendar dates with at least one captured notice: 22

The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.

YearHot water below standard, hoursDates with a noticeHeating below standard, hoursHot water off, hoursHeating off, hours
20251902218513835
2026*26910364

* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.

Last captured notice (original, in Romanian) · 2026-10-08 12:43

Remediere avarie circuit primar

• Str Fabricii - bl. 15E, 15D, 15C, 25/III, 25/IV, 25/V • Bld Iuliu Maniu - bl. 15bis, 15A, 15B • Ale Cetăţuia - bl. 25/I, 25/II

Streets named in the notices

Outages and their causes, on this substation’s page in “Why your hot water is off”

The cold in the contract →