Heat substation 4 Lanariei: hours of below-standard hot water, 2025–2026
Sector 4
250 national threshold: 250 hours per year and contract · local threshold: total waiver
Calendar dates with at least one captured notice: 17
The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.
| Year | Hot water below standard, hours | Dates with a notice | Heating below standard, hours | Hot water off, hours | Heating off, hours |
|---|---|---|---|---|---|
| 2025 | 92 | 17 | 6 | 836 | 387 |
| 2026* | 78 | 15 | 13 | 1,250 | 282 |
* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.
Last captured notice (original, in Romanian) · 2026-10-09 23:05
La punerea in functiune a aparut o noua avarie care necesita inlocuirea a aproximativ 60 m conductă DN 600
• Str Avalanşei - bl. 1, 2, 3 • Bld Gheorghe Şincai - bl. 2, 3, 3TR1, 4, 5, 5A • Str Cuza Vodă - bl. 1A
Streets named in the notices
- Str Avalanşei
- Bld Gheorghe Şincai
- Str Cuza Vodă