Heat substation 6 Mărășești: hours of below-standard hot water, 2025–2026
Sector 3
250 national threshold: 250 hours per year and contract · local threshold: total waiver
Calendar dates with at least one captured notice: 17
The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.
| Year | Hot water below standard, hours | Dates with a notice | Heating below standard, hours | Hot water off, hours | Heating off, hours |
|---|---|---|---|---|---|
| 2025 | 99 | 17 | 222 | 559 | 244 |
| 2026* | 253 | 26 | 321 | 407 | 11 |
* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.
Last captured notice (original, in Romanian) · 2026-10-17 12:00
Avarie CR-ACC bl. M6 sc.1 / bd. Mircea Voda.
• Bld Mircea Vodă - bl. M11, M14, M20bis, M9,M8, M1, M21, M22, M6, M20 • Str Panait Cerna - bl. M5 • Spl Unirii - bl. M3, M4, M12, M19, M10, M15, M7, M18, M16, M13
Streets named in the notices
- Bld Mircea Vodă
- Str Panait Cerna
- Spl Unirii
Outages and their causes, on this substation’s page in “Why your hot water is off”