Heat substation 6 Margeanului: hours of below-standard hot water, 2025–2026
Sector 5
250 national threshold: 250 hours per year and contract · local threshold: total waiver
Calendar dates with at least one captured notice: 17
The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.
| Year | Hot water below standard, hours | Dates with a notice | Heating below standard, hours | Hot water off, hours | Heating off, hours |
|---|---|---|---|---|---|
| 2025 | 120 | 17 | 310 | 613 | 161 |
| 2026* | 30 | 11 | 10 | 493 | 3 |
* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.
Last captured notice (original, in Romanian) · 2026-10-14 17:01
Lucrări de reabilitare a sistemului de termoficare al Municipiului Bucuresti executate de către Asocierea Energomontaj SA (lider) - SC Elsaco Electronic SRL - SC Sicor SRL și IPCT Instalatii SRL
• Str Cap. Ivan Anghelache - bl. M21, M25, M26, M27 • Str Sold. Ene Modoran - bl. M91, M92, M94 • Str Dumbrava Nouă - bl. M17, M28, M80, M81, M82 • Str Cap. Petre Mişcă - bl. M18, M19, M20, M22 • Str Mărgeanului - bl. M23, M23A, M24
Streets named in the notices
- Str Cap. Ivan Anghelache
- Str Sold. Ene Modoran
- Str Dumbrava Nouă
- Str Cap. Petre Mişcă
- Str Mărgeanului
- Str Dumbrava Nouă - M80
Outages and their causes, on this substation’s page in “Why your hot water is off”