Heat substation 7 Lavandei: hours of below-standard hot water, 2025–2026
Sector 6
250 national threshold: 250 hours per year and contract · local threshold: total waiver
Calendar dates with at least one captured notice: 51
The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.
| Year | Hot water below standard, hours | Dates with a notice | Heating below standard, hours | Hot water off, hours | Heating off, hours |
|---|---|---|---|---|---|
| 2025 | 268 | 51 | 249 | 106 | 19 |
| 2026* | 81 | 21 | 32 | 112 | 30 |
* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.
Last captured notice (original, in Romanian) · 2026-10-18 19:38
Funcționare deficitară a apei calde de consum
• Str Lavandei - bl. P28 • Str Dobreni - bl. P22, P23 • Int Pitulicii - bl. P24, P25, P26, P27 • Str Dezrobirii - bl. P17, P19 • Bld Uverturii - bl. P16, P21 • Str Cernişoara - bl. P18, P20, O13
Streets named in the notices
- Str Lavandei
- Str Dobreni
- Int Pitulicii
- Str Dezrobirii
- Bld Uverturii
- Str Cernişoara
Outages and their causes, on this substation’s page in “Why your hot water is off”