The cold in the contract

Heat substation 7 Placare-T: hours of below-standard hot water, 2025–2026

Sector 3

162Reconstructed hours with a notice of hot water below standard · in 2025

250 national threshold: 250 hours per year and contract · local threshold: total waiver

Calendar dates with at least one captured notice: 15

The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.

YearHot water below standard, hoursDates with a noticeHeating below standard, hoursHot water off, hoursHeating off, hours
2025162150274103
2026*296371803220

* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.

Last captured notice (original, in Romanian) · 2026-09-17 14:55

Lipsa parametri pentru livrare apa calda de consum

• Str Ticuş - bl. M31A, M31B • Bld Nicolae Grigorescu - bl. S1D, M32A • Ale Ilioara - bl. M30A, M30B, M30C, M31, M32 • Bld Camil Ressu - bl. S1A, S1B-S1C, S2

Streets named in the notices

Outages and their causes, on this substation’s page in “Why your hot water is off”

The cold in the contract →