Heat substation 8/5: hours of below-standard hot water, 2025–2026
Sector 6
250 national threshold: 250 hours per year and contract · local threshold: total waiver
Calendar dates with at least one captured notice: 23
The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.
| Year | Hot water below standard, hours | Dates with a notice | Heating below standard, hours | Hot water off, hours | Heating off, hours |
|---|---|---|---|---|---|
| 2025 | 195 | 23 | 188 | 111 | 0 |
| 2026* | 54 | 13 | 0 | 34 | 4 |
* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.
Last captured notice (original, in Romanian) · 2026-09-08 11:59
Parametri insuficienti furnizati de CTE Grozavesti
• Ale Parva - bl.D23,C37, A35 • Str Drumul Taberei - bl.C8 • Ale Băiuţ - bl.M29, M29 Bis,A34, C7 Bis, C36 • Str Valea Ialomiţei - bl.C18A+B, D22, D21, D20
Streets named in the notices
- Ale Parva
- Str Drumul Taberei
- Ale Băiuţ
- Str Valea Ialomiţei
Outages and their causes, on this substation’s page in “Why your hot water is off”