Heat substation P 5 A: hours of below-standard hot water, 2025–2026
Sector 4
250 national threshold: 250 hours per year and contract · local threshold: total waiver
Calendar dates with at least one captured notice: 19
The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.
| Year | Hot water below standard, hours | Dates with a notice | Heating below standard, hours | Hot water off, hours | Heating off, hours |
|---|---|---|---|---|---|
| 2025 | 114 | 19 | 60 | 1,086 | 230 |
| 2026* | 151 | 20 | 200 | 381 | 51 |
* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.
Last captured notice (original, in Romanian) · 2026-10-23 07:42
Lucrari de reabilitare a sistemului de termoficare al Municipiului Bucuresti, Lot 3 - Obiectiv 15
• Bld Dimitrie Cantemir - bl. P1, P2, P3 • Str Bibescu Vodă - bl. P4, P5, P5A
Streets named in the notices
- Bld Dimitrie Cantemir
- Str Bibescu Vodă
Outages and their causes, on this substation’s page in “Why your hot water is off”