Heat substation Sincai: hours of below-standard hot water, 2025–2026

Sector 4

96Reconstructed hours with a notice of hot water below standard · in 2025

250 national threshold: 250 hours per year and contract · local threshold: total waiver

Calendar dates with at least one captured notice: 19

The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.

YearHot water below standard, hoursDates with a noticeHeating below standard, hoursHot water off, hoursHeating off, hours
202596194817348
2026*11324161,281282

* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.

Last captured notice (original, in Romanian) · 2026-10-23 07:42

Lipsa parametri pentru livrare apă caldă de consum

• Str Mocăncuţei - Imobil nr.12 • Bld Gheorghe Şincai - bl. 2, 4 • Str Tineretului - bl 5,Z1 • Str Trestiana - bl. 3 • Str Constantin Rădulescu-Motru - bl. 1, 35 • Str Cuza Vodă - bl. 37A

Streets named in the notices

Outages and their causes, on this substation’s page in “Why your hot water is off”